Evaluating the upgrade potential of Uganda’s 132 kV transmission lines to 220 kV: Nkenda to Mbarara South as a case Study
Mwanja Grace Charles, Aliyu Nuhu Shuaibu, Ogwal Emmanuel, Venkataramana Guntreddi
Published December 29, 2024
Pages 77-83
This study examines the feasibility of upgrading Uganda’s 132 kV transmission lines to 220 kV, using the Nkenda to Mbarara South line as a case study. The primary focus is to mitigate power losses, improve system efficiency, and enhance voltage regulation. The research employs the Nominal Pi-model in MATLAB to verify line parameters, evaluate performance indicators (efficiency, power factor, and voltage regulation), and assess economic viability through a Net Present Value (NPV) analysis. Findings reveal that the upgrade would reduce power losses by 68%, increase efficiency to 98.77%, and lower voltage regulation by 7.69%. The study concludes that the upgrade is both technically and economically viable, offering long-term benefits to Uganda’s energy infrastructure. Recommendations include the immediate implementation of the 220 kV upgrade and the development of policies to optimize transmission system investments.
Power Losses
System Efficiency
Voltage Regulation
Economic Feasibility
Transmission Line Upgrade
Uganda Energy Infrastructure
Mwanja Grace Charles, Aliyu Nuhu Shuaibu, Ogwal Emmanuel, Venkataramana Guntreddi.
"Evaluating the upgrade potential of Uganda’s 132 kV transmission lines to 220 kV: Nkenda to Mbarara South as a case Study."
KIU Journal of Science, Engineering and Technology
, vol. 3
, no. 2
, 2024
, pp. 77-83